CROSS Safety Report

Safe use of lifting magnets

Report ID: 849 Published: 1 October 2019 Region: CROSS-UK

This report is over 2 years old

Please be aware that it might contain information that is no longer up to date. We keep all reports available for historic reference and as learning aids.

Overview

A reporter highlights how a two-tonne lift using magnetic lifting equipment was abandoned, averting a potential high consequence event.

Key Learning Outcomes

For construction professionals and designers:

  • Early consultation with the lifting equipment suppliers to identify all factors that can affect the safe working load of equipment is good practice

  • Be aware that all lifting operations involving lifting equipment should be properly designed, planned and supervised by a person who is competent to do so

  • A holistic understanding of plant and equipment procured through hire companies along with the risks associated in their safe use should be communicated to the operatives on site

  • The Lifting Equipment Engineers Association (LEEA) website contains useful information on this topic

Full Report

Find out more about the Full Report

Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others. If you would like to know more, please visit the reporting to CROSS-AUS page. 

A two-tonne footway panel lift using magnetic lifting equipment was abandoned, averting a potential low-probability high-consequence event, says a reporter. The number and safe working load of the lifting magnets, the centre of gravity of the panel, shackles, slings, lifting frame and crane load chart capacity were all reviewed and approved.

However, the 7mm thick panel was less than the minimum material thickness required to obtain a ‘closed circuit’ and 100% magnetic clamping force. This significantly compromised the hold integrity of the lifting magnets. Without sufficient magnetic clamping force, the panel was dropped uncontrolled without serious damage.

Constraints of lifting magnets

The operation was reported as a close call noting that the lifting magnets hired required a minimum flat steel thickness of 60mm to achieve the one-tonne per magnet safe working load. The lift was abandoned until suitable lifting magnets were sourced from a different supplier capable of achieving the safe working load with the constraint of the 7mm thick panel.

Role of designer under CDM

The reporter points out that anyone who specifies a particular method of work is considered a designer under the Construction Design and Management (CDM) Regulations 2015. By proposing to source lifting magnets instead of fabricating lifting eyes to fit the panel, the contractor specified a method of work, effectively taking on the role of the designer, says the reporter.

The reporter aims to highlight the following key points from this incident:

  • During procurement, lifting magnet suppliers have a duty of care to inform the industry of the factors affecting the safe working load

  • Air gaps, material type, contact area and material thickness affect the magnetic clamping force between lifting magnets and the load

  • The capacity of the crane, lifting frame, slings and shackles are often checked in risk assessments and lifting checklists. Risk assessments and lifting checklists should be revised to allow for other available products in the market

  • A holistic understanding of plant and equipment procured through hire companies along with the risks associated in their safe use must be communicated to the operatives on site

A holistic understanding of plant and equipment procured through hire companies along with the risks associated in their safe use must be communicated to the operatives on site

Expert Panel Comments

Find out more about the Expert Panel

An Expert Panel comment on the reports we receive. They use their experience to help you understand what can be learned from the reports. If you would like to know more, please visit the CROSS-AUS Expert Panel page.

It is fortunate that this event was a close call rather than what might have happened if the lift had proceeded. The report highlights a risk since non-specialists would be most unlikely to have the experience to understand constraints that might apply to this lifting methodology. An important but often overlooked safety mitigation measure is to have a prescribed exclusion zone. This can ensure people are excluded from any potential for fall during lifting operations.

The planning of lifting operations

Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) place duties on people and companies who own, operate or have control over lifting equipment. In most cases, lifting equipment is also work equipment so the Provision and Use of Work Equipment Regulations 1998 (PUWER) will also apply (including inspection and maintenance). All lifting operations involving lifting equipment must be properly planned by a competent person, appropriately supervised and carried out in a safe manner. The Lifting Equipment Engineers Association (LEEA) website contains useful information on this topic.

All lifting operations involving lifting equipment must be properly planned by a competent person, appropriately supervised and carried out in a safe manner. The Lifting Equipment Engineers Association (LEEA) website contains useful information on this topic.

Who counts as a designer under CDM 2015?

The HSE published guidance on the Construction (Design and Management) Regulations 2015 which states that a designer is an organisation or individual, who:

a) prepares or modifies a design for a construction project (including the design of temporary works); or

b) arranges for, or instructs someone else to do so.

 

The document goes on to say that the term ‘design’ includes drawings, design details, specifications, bills of quantity and calculations prepared for the purpose of a design. Designers can include:

  • Architects

  • Architectural technologists

  • Consulting engineers

  • Quantity surveyor

  • Interior designers

  • Temporary work engineers

  • Chartered Surveyors

  • Technicians or anyone who specifies or alters a design

Magnetic lifting is routinely and safely used in many industries, for example in ship building, where there is more familiarity with the methodology.